2.5MW Biogas/Natural Gas – Huddersfield

Sector

Water Industry

Location

Huddersfield

Fuel

Biogas/natural gas

Key Benefit

Energy Security

Services Provided

  • Design and installation of a bespoke pre-fabricated plant room
  • Design and installation of dual fuel biogas/natural gas boiler plant
  • Installation of a bespoke control panel
  • Commissioning

Plant Room

A bespoke flat panelled steel building houses:

  • Viessmann Boiler
  • Riello Burner
  • Manifold
  • Pressurisation and expansion control
  • Biogas booster and acoustic shroud
  • Bespoke LCP
  • 2.5MW gasket PHE
  • System loading pumps

Heat Usage

  • Process heat for anaerobic digestion and de-watering plant

More Information

The client required a backup dual fuel boiler to provide heat to the anaerobic digestion and de-watering plant in the event of CHP downtime or biological failure. We provided a bespoke pre-packaged plant manufactured and soft commissioned in our workshop.

The plant was delivered to the site, craned into position on a 4-meter high concrete mezzanine. The mechanical and electrical installation was completed before onsite commissioning.